No. Job Name Job Description NO. of Employees Duration Action Status
1 Prepare Construction Site and Pour Foundation
  • Apply for and Acquire Permits
  • Construction Crew Levels Site
  • Puts Up Wooden Forms for the Temporary Foundation
  • Footings Are Installed
  • 15 45 Days
    2 Complete Rough Framing
  • Floor System, Walls, Roof Systems Are Completed
  • Sheathing Applied to Exterior Walls, Covered With Protective Wrap
  • 25 90 Days
    3 Complete Rough Plumbing, Electrical HVAC The Following Are Installed:
  • Pipes and Wires
  • Sewer Lines and Vents
  • Water Supply Lines
  • Bathtubs,Shower Units
  • Ductwork for HVAC System
  • HVAC Vent Pipes
  • 20 65 Days
    4 Install Insulation Common Types of Insulation in New Homes
  • Fiberglass
  • Cellulose
  • Foam Mineral Wool
  • Concrete Blocks
  • Insulation Concrete Forms
  • Spray Foam
  • Structural Insulated Panels
  • Foam Board or Ridged Foam
  • 15 50 Days
    5 Complete Drywall and Interior Fixtures, Start Exterior Finishes
  • Drywall is Hung and Taped
  • Texturing is Completed
  • Primary Coat of Paint is Applied
  • Exterior Finishes (Brick, Stucco, Stone) Are Installed
  • 20 50 Days
    6 Finish Interior Trim, Install Exterior Walkways and Driveway
  • Doors, Window Sills, Decorative Trim Installed
  • Cabinets, Vanities, Fireplace Mantles Installed
  • Final Coat of Paint
  • 20 40 Days
    7 Install Hard Surface Flooring, Countertops; Complete Exterior Grading Ceramic tile, vinyl and wood flooring are installed as well as countertops. Exterior finish grading is completed to ensure proper drainage away from the home and prepare the yard for landscaping. 15 25 Days
    8 Finish Mechanical Trims; Install Bathroom Fixtures Light fixtures, outlets and switches are installed and the electrical panel is completed. HVAC equipment is installed and registers completed. Sinks, toilets and faucets are put in place. 8 25 Days
    9 Install Mirrors, Shower Doors; Finish Flooring, Exterior Landscaping Mirrors, shower doors and carpeting are installed and final cleanup takes place. Trees, shrubs and grass are planted and other exterior landscaping completed. 6 15 Days
    10 Final Walk-Through This is where you spot items that need to be corrected or adjusted! 3 5 Days