Sheathing Applied to Exterior Walls, Covered With
Protective Wrap
25
90 Days
3
Complete Rough Plumbing, Electrical HVAC
The Following Are Installed:
Pipes and Wires
Sewer Lines and Vents
Water Supply Lines
Bathtubs,Shower Units
Ductwork for HVAC System
HVAC Vent Pipes
20
65 Days
4
Install Insulation
Common Types of Insulation in New Homes
Fiberglass
Cellulose
Foam Mineral Wool
Concrete Blocks
Insulation Concrete Forms
Spray Foam
Structural Insulated Panels
Foam Board or Ridged Foam
15
50 Days
5
Complete Drywall and Interior Fixtures, Start
Exterior Finishes
Drywall is Hung and Taped
Texturing is Completed
Primary Coat of Paint is Applied
Exterior Finishes (Brick, Stucco, Stone) Are
Installed
20
50 Days
6
Finish Interior Trim, Install Exterior Walkways and
Driveway
Doors, Window Sills, Decorative Trim Installed
Cabinets, Vanities, Fireplace Mantles Installed
Final Coat of Paint
20
40 Days
7
Install Hard Surface Flooring, Countertops; Complete
Exterior Grading
Ceramic tile, vinyl and wood flooring are installed
as well as countertops. Exterior finish grading is
completed to ensure proper drainage away from the
home and prepare the yard for landscaping.
Light fixtures, outlets and switches are installed
and the electrical panel is completed. HVAC
equipment is installed and registers completed.
Sinks, toilets and faucets are put in place.
Mirrors, shower doors and carpeting are installed
and final cleanup takes place. Trees, shrubs and
grass are planted and other exterior landscaping
completed.
6
15 Days
10
Final Walk-Through
This is where you spot items that need to be
corrected or adjusted!