Budget Management


Budget Information

No. Reason Name No. of Employees Duration Price Action
1 Designing 2 10 days 60,000 Birr
2 Drilling 10 20 days 130,000 Birr
3 Slab 10 55 days 200,000 Birr
4 Partition 13 65 days 180,000 Birr
5 Plumbing 10 35 Days 75,000 Birr
6 Roofing 6 25 Days 75,000 Birr
7 Flooring 10 25 Days 75,000 Birr
8 Finishing 24 45 days 150,000 Birr